Computer Center Refurbishment
   

The preparations for the installations of the new transformer sub-station started in September 2003.

.

And were finished including the electrical connections by September 2004.

 

Emptying the right half of the computer center

After refurbishment , filling it again with equipment.

The equipment in the newly created vault area.

 

 

The network area.

 

The openlab area.

 

Cleaning of the left side of the computer center.

 

 

 

 

 

 
 
 
 